{"id":2166,"date":"2018-02-05T13:16:39","date_gmt":"2018-02-05T19:16:39","guid":{"rendered":"http:\/\/www.ojoconmipisto.com\/open-contracting\/?p=2166"},"modified":"2019-02-07T19:03:29","modified_gmt":"2019-02-08T01:03:29","slug":"san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada","status":"publish","type":"post","link":"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/","title":{"rendered":"Terminal de buses que cost\u00f3 Q14.9 millones, estancada"},"content":{"rendered":"

 <\/p>\n

 <\/p>\n

El proyecto debi\u00f3 finalizar hace tres a\u00f1os y medio. La alcald\u00eda de San Pedro Soloma y la empresa prorrogaron el plazo cinco veces, y la Contralor\u00eda repar\u00f3 en el proyecto.<\/h4>\n

 <\/p>\n

 <\/p>\n

Por Isa\u00edas Morales |\u00a05 de febrero de 2018<\/em><\/p>\n

 <\/p>\n

 <\/p>\n

La municipalidad de San Pedro Soloma (Huehuetenango) y la constructora Inciarc mantienen un proceso en el Tribunal de lo Contencioso Administrativo para reiniciar o no la construcci\u00f3n de la Terminal de buses de la localidad, cuyo costo asciende a Q14.9 millones<\/a>. Esta obra tuvo que finalizar el 22 de agosto de 2014, pero tres hallazgos de la Contralor\u00eda General de Cuentas, las condiciones clim\u00e1ticas y las disputas legales frenaron su ejecuci\u00f3n.<\/p>\n

Desde hace tres a\u00f1os la primera fase del proyecto \u201cTerminal de buses y central de abastos de agua tibia\u201d debi\u00f3 estar concluido, pero el anterior alcalde Nicol\u00e1s Mart\u00ednez (2012-2016) y la constructora prorrogaron el contrato n\u00famero 12-2013 durante cinco veces. La \u00faltima modificaci\u00f3n se firm\u00f3 el 9 de diciembre de 2015.<\/p>\n

Con este nuevo acuerdo la terminal iba a estar lista el 22 de abril de 2016, pero al asumir el alcalde Gregorio L\u00f3pez Joaqu\u00edn decidi\u00f3 suspenderla de nuevo. Odenilson L\u00f3pez Rodr\u00edguez, copropietario de Inciarc, culpa a la actual administraci\u00f3n, pero admite que la anterior tambi\u00e9n tuvo responsabilidad en que la ejecuci\u00f3n se estancara.<\/p>\n

 <\/p>\n

Deficiencias en planificaci\u00f3n y reportes<\/strong><\/h4>\n

 <\/p>\n

Seg\u00fan una auditor\u00eda a la infraestructura<\/a> de San Pedro Soloma, realizada por la Contralor\u00eda en 2015, la municipalidad incumpli\u00f3 con tres aspectos t\u00e9cnicos en este proyecto.<\/p>\n

Primero el ente fiscalizador detect\u00f3 que la municipalidad report\u00f3 un 85 por ciento de avance f\u00edsico y los auditores estimaron un 10 por ciento menos. Luego el entonces alcalde Mart\u00ednez no exigi\u00f3 a la empresa realizar pruebas de laboratorio para verificar la calidad de los materiales.<\/p>\n

Adem\u00e1s, el Estudio de Impacto Ambiental (EIA-0085-2014) fue tramitado posterior a la firma del contrato y no antes. El Ministerio de Ambienta y Recursos Naturales la recibi\u00f3 el 14 de marzo de 2014 y la aval\u00f3 el 5 de mayo.<\/p>\n

Ante ello la Contralor\u00eda General de Cuentas emiti\u00f3 tres multas contra el alcalde Mart\u00ednez cuyo monto ascendi\u00f3 a Q30 mil en total.<\/p>\n

 <\/p>\n

Municipalidad vs constructora<\/h4>\n

 <\/p>\n

La municipalidad y la constructora dilucidan la situaci\u00f3n en el Tribunal Contencioso de lo Administrativo. El empresario Odenilson L\u00f3pez atribuye lo sucedido a motivos pol\u00edticos del alcalde.<\/p>\n

Por su parte, el alcalde se reh\u00fasa a dar explicaciones sobre el tema. \u201cNo voy a contestar preguntas por tel\u00e9fono a alguien que no conozco\u201d, respondi\u00f3 v\u00eda telef\u00f3nica al consultarle su versi\u00f3n.<\/p>\n

Una de las justificaciones de la alcald\u00eda, seg\u00fan la constructora, es la falta de recursos para solventar los pagos. \u201cEso es lo que dicen ellos, pero tambi\u00e9n es por razones pol\u00edticas. El anterior alcalde prometi\u00f3 concluir el proyecto si se reeleg\u00eda, y el que qued\u00f3 (electo) prometi\u00f3 no continuarlo\u201d<\/p>\n

La municipalidad logr\u00f3 financiar todo el proyecto con apoyo del Instituto de Fomento Municipal (Infom). Hasta la fecha esta ya fue pagada<\/a>. Sin embargo L\u00f3pez Rodr\u00edguez asegura que a\u00fan hay un saldo pendiente de solventar con \u00e9l.<\/p>\n

\u201cProcedimos a defendernos por la v\u00eda judicial, tenemos un dictamen de la Contralor\u00eda donde pide finalizar la obra. Solo nos falta un ocho por ciento de avance f\u00edsico. Soy de la idea que finalicemos la obra, pero la municipalidad no tiene voluntad de hacerlo\u201d, agreg\u00f3.<\/p>\n

El portal del Sistema Nacional de Inversi\u00f3n P\u00fablica (SNIP) de la Secretar\u00eda General de Planificaci\u00f3n de la Presidencia (Segeplan) da cuenta que la municipalidad report\u00f3 un 88 por ciento de avance f\u00edsico y 84 por ciento hasta el 11 de noviembre de 2014<\/a>. Luego de esa fecha no se report\u00f3 ning\u00fan otro avance<\/a>.<\/p>\n

 <\/p>\n


\n

 <\/p>\n

Esta nota es producto del Diplomado \u201cPeriodismo y Desigualdades\u201d impartido por Laboratorio de Medios, S.A., a comunicadores de varios departamentos de Guatemala con financiamiento de Oxfam y la Inter-American Foundation (IAF). El contenido es exclusiva responsabilidad de su autor.<\/em><\/p>\n","protected":false},"excerpt":{"rendered":"

    El proyecto debi\u00f3 finalizar hace tres a\u00f1os y medio. La alcald\u00eda de San Pedro Soloma y la empresa prorrogaron el plazo cinco veces, y la Contralor\u00eda repar\u00f3 en el proyecto.     Por Isa\u00edas Morales |\u00a05 de febrero de 2018     La…<\/p>\n","protected":false},"author":34,"featured_media":2167,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":[],"categories":[34],"tags":[],"yoast_head":"\nTerminal de buses que cost\u00f3 Q14.9 millones, estancada - Open Contracting<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/\" \/>\n<meta property=\"og:locale\" content=\"es_ES\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Terminal de buses que cost\u00f3 Q14.9 millones, estancada - Open Contracting\" \/>\n<meta property=\"og:description\" content=\"    El proyecto debi\u00f3 finalizar hace tres a\u00f1os y medio. La alcald\u00eda de San Pedro Soloma y la empresa prorrogaron el plazo cinco veces, y la Contralor\u00eda repar\u00f3 en el proyecto.     Por Isa\u00edas Morales |\u00a05 de febrero de 2018     La...\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/\" \/>\n<meta property=\"og:site_name\" content=\"Open Contracting\" \/>\n<meta property=\"article:published_time\" content=\"2018-02-05T19:16:39+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2019-02-08T01:03:29+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-content\/uploads\/sites\/4\/2019\/02\/San-Pedro-Soloma.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1280\" \/>\n\t<meta property=\"og:image:height\" content=\"960\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Laboratorio de Medios\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Escrito por\" \/>\n\t<meta name=\"twitter:data1\" content=\"Laboratorio de Medios\" \/>\n\t<meta name=\"twitter:label2\" content=\"Tiempo de lectura\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutos\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"WebPage\",\"@id\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/\",\"url\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/\",\"name\":\"Terminal de buses que cost\u00f3 Q14.9 millones, estancada - Open Contracting\",\"isPartOf\":{\"@id\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/#website\"},\"datePublished\":\"2018-02-05T19:16:39+00:00\",\"dateModified\":\"2019-02-08T01:03:29+00:00\",\"author\":{\"@id\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/#\/schema\/person\/549ca9c2719108a6c2764025bf919737\"},\"breadcrumb\":{\"@id\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/#breadcrumb\"},\"inLanguage\":\"es\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/\"]}]},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Portada\",\"item\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Terminal de buses que cost\u00f3 Q14.9 millones, estancada\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/#website\",\"url\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/\",\"name\":\"Open Contracting\",\"description\":\"Ojoconmipisto\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/?s={search_term_string}\"},\"query-input\":\"required name=search_term_string\"}],\"inLanguage\":\"es\"},{\"@type\":\"Person\",\"@id\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/#\/schema\/person\/549ca9c2719108a6c2764025bf919737\",\"name\":\"Laboratorio de Medios\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"es\",\"@id\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/864ce428f4ff2c7b702453044f1e9d2f?s=96&d=mm&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/864ce428f4ff2c7b702453044f1e9d2f?s=96&d=mm&r=g\",\"caption\":\"Laboratorio de Medios\"},\"sameAs\":[\"http:\/\/ojoconmipisto.com\"],\"url\":\"https:\/\/www.ojoconmipisto.com\/open-contracting\/author\/labmedios\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Terminal de buses que cost\u00f3 Q14.9 millones, estancada - Open Contracting","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/","og_locale":"es_ES","og_type":"article","og_title":"Terminal de buses que cost\u00f3 Q14.9 millones, estancada - Open Contracting","og_description":"    El proyecto debi\u00f3 finalizar hace tres a\u00f1os y medio. La alcald\u00eda de San Pedro Soloma y la empresa prorrogaron el plazo cinco veces, y la Contralor\u00eda repar\u00f3 en el proyecto.     Por Isa\u00edas Morales |\u00a05 de febrero de 2018     La...","og_url":"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/","og_site_name":"Open Contracting","article_published_time":"2018-02-05T19:16:39+00:00","article_modified_time":"2019-02-08T01:03:29+00:00","og_image":[{"width":1280,"height":960,"url":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-content\/uploads\/sites\/4\/2019\/02\/San-Pedro-Soloma.jpg","type":"image\/jpeg"}],"author":"Laboratorio de Medios","twitter_card":"summary_large_image","twitter_misc":{"Escrito por":"Laboratorio de Medios","Tiempo de lectura":"3 minutos"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/","url":"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/","name":"Terminal de buses que cost\u00f3 Q14.9 millones, estancada - Open Contracting","isPartOf":{"@id":"https:\/\/www.ojoconmipisto.com\/open-contracting\/#website"},"datePublished":"2018-02-05T19:16:39+00:00","dateModified":"2019-02-08T01:03:29+00:00","author":{"@id":"https:\/\/www.ojoconmipisto.com\/open-contracting\/#\/schema\/person\/549ca9c2719108a6c2764025bf919737"},"breadcrumb":{"@id":"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/#breadcrumb"},"inLanguage":"es","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/"]}]},{"@type":"BreadcrumbList","@id":"https:\/\/www.ojoconmipisto.com\/open-contracting\/san-pedro-soloma-terminal-de-buses-que-costo-q14-9-millones-estancada\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Portada","item":"https:\/\/www.ojoconmipisto.com\/open-contracting\/"},{"@type":"ListItem","position":2,"name":"Terminal de buses que cost\u00f3 Q14.9 millones, estancada"}]},{"@type":"WebSite","@id":"https:\/\/www.ojoconmipisto.com\/open-contracting\/#website","url":"https:\/\/www.ojoconmipisto.com\/open-contracting\/","name":"Open Contracting","description":"Ojoconmipisto","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.ojoconmipisto.com\/open-contracting\/?s={search_term_string}"},"query-input":"required name=search_term_string"}],"inLanguage":"es"},{"@type":"Person","@id":"https:\/\/www.ojoconmipisto.com\/open-contracting\/#\/schema\/person\/549ca9c2719108a6c2764025bf919737","name":"Laboratorio de Medios","image":{"@type":"ImageObject","inLanguage":"es","@id":"https:\/\/www.ojoconmipisto.com\/open-contracting\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/864ce428f4ff2c7b702453044f1e9d2f?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/864ce428f4ff2c7b702453044f1e9d2f?s=96&d=mm&r=g","caption":"Laboratorio de Medios"},"sameAs":["http:\/\/ojoconmipisto.com"],"url":"https:\/\/www.ojoconmipisto.com\/open-contracting\/author\/labmedios\/"}]}},"_links":{"self":[{"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/posts\/2166"}],"collection":[{"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/users\/34"}],"replies":[{"embeddable":true,"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/comments?post=2166"}],"version-history":[{"count":3,"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/posts\/2166\/revisions"}],"predecessor-version":[{"id":2250,"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/posts\/2166\/revisions\/2250"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/media\/2167"}],"wp:attachment":[{"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/media?parent=2166"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/categories?post=2166"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.ojoconmipisto.com\/open-contracting\/wp-json\/wp\/v2\/tags?post=2166"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}